A new production site with no grid needed 20 kW of three-phase power it could rely on. We built twelve 48 V LiFePO₄ batteries for it, supplied a Deye hybrid inverter, fitted out the rack with busbars and breakers, and commissioned the system on site with a gas generator as the charger. Every figure on this page comes from our own record of the build and commissioning.
The task: power for a production site with no grid
A manufacturer was starting up a new production site with no grid connection at all. Power had to come from a gas generator fed by an underground gas tank — but running a generator around the clock for every load is noisy, expensive and wears the engine. The site needed a 20 kW, three-phase uninterruptible power system: a battery bank that carries the load, an inverter that makes 220/380 V for the workshop, and the generator working only as a charger. Solar panels can be added to the same inverter later.
What we delivered, turnkey
- Twelve LiFePO₄ batteries of our own build, 48 V and 105 Ah each, with a BMS that talks to the inverter.
- A Deye 20 kW three-phase hybrid inverter, selected and supplied by us.
- A distribution board on the battery rack: four-way power busbars and two-pole breakers for each shelf, with polycarbonate covers.
- Busbars made for this project: our design, our 3D-printed parts, our laser-cut copper.
- Wiring, the battery network and commissioning on site, until the system ran with no errors.
The gas tank and the generator were installed by a partner company we worked with directly.
The system at a glance
| Part | Specification |
|---|---|
| Inverter | Deye hybrid, 20 kW, three-phase, 220/380 V output |
| Batteries | 12 × LiFePO₄, 51.2 V nominal (16 cells in series), 105 Ah each, in parallel |
| Total capacity | 1,260 Ah ≈ 64.5 kWh |
| Cells | EVE, grade A, current-year production |
| Measured capacity | 110 Ah per battery at 40 A — 5% above the rating |
| BMS | Inverter communication, 4 temperature sensors, built-in 2 A balancer, touchscreen |
| Charging source | 30 kW gas generator through the inverter; solar can be added |
| Charge / discharge limit | 300 A / 300 A (the inverter allows 350 A) |
Building each battery
Each battery starts with sixteen prismatic LiFePO₄ cells. We check every cell with a meter for two values — voltage and internal resistance — and both must be within the datasheet limits and close to the neighbours' values. The cells are EVE grade A from the current year's production: fresh cells, and a capacity above the rating, which the test later confirmed.
The cells go into plastic holders — prismatic cells have them too, like small 18650 and 21700 cells. Holders make the battery body rigid and keep the cells under even compression, which prismatic cells need to resist swelling and keep their life. Two rows of eight cells are connected in series with busbars, the bolts set on thread-locker, and the voltage at the terminals is checked before going further.
The BMS sits in a holder we designed and 3D-printed for this battery. Every balance lead is routed to its place, cut to length, tinned and soldered to the board — soldered, not crimped. Four external temperature sensors are spread along the cells, so the battery's temperature reading is an average of the whole body, not one spot.
Why the BMS has to talk to the inverter
Many backup systems run on batteries without a BMS, or on lead-acid: the inverter gets a plus and a minus and nothing else. It sees the voltage and nothing more — not the temperature, not the remaining capacity of each battery, not a fault inside the chain — and keeps working as if nothing happened, even if one battery is overheating. In this system the BMS and the inverter exchange voltage, current, state of charge, temperature, limits and alarms, so every battery is under two layers of control: the BMS protection and the inverter's algorithms.
The boards here have the full option set: an external communication interface and a touchscreen in a bezel we drew and printed, set into the front of the case. With twelve batteries this matters — a phone app connects to only one board at a time.
Balancing: 2 A built in
This BMS has a built-in balancer of 2,000 mA. That is unusual: most BMS boards balance passively at tens to a few hundred milliamps, and 1–2 A of active balancing is found only on the better smart boards. It runs on its own — switching on when the difference between cells grows and off when it is back in range — so the owner never has to think about it. On batteries where a board of this level makes no sense, we fit separate active balancers of up to 5,000 mA, also controlled by the BMS.
The capacity test: 110 Ah from a 105 Ah battery
Every battery we ship goes through a full laboratory cycle, whatever it costs and whatever it is for. It is charged, balanced, and then discharged at 40 A — above the 25 A each battery delivers in this system at the 300 A limit — so the test is harder than real working conditions. Adding up both load units gave 110 Ah: the real capacity of these grade-A cells is 5% above the rating.
A case that can be opened
The battery is packed into its case with padding on the sides and on top, and a sealing cord goes into the groove of the lid. The lid is not glued, welded or screwed into plastic: it is bolted through brass threaded inserts. The case stays sealed, and the battery can be opened for service as many times as needed, with no sealant to scrape off and reapply.
Before shipping each battery is charged to about 30% — enough to test everything on site and to watch it charge from the inverter — and marked with its own number, used during commissioning and later for remote support.
On site: the rack, the busbars and the battery network
The batteries went onto an ordinary warehouse rack, so we first fitted it out: a distribution board with four-way power busbars and two-pole breakers that feed the inverter. On each of the three shelves four batteries are joined in parallel with busbars made for this project — four minuses to the black bar, four pluses to the red — and the shelves are then joined, so all twelve batteries form one power circuit.
Power is half the job; the batteries also have to talk. Network cables run from the last battery along each shelf and up to the next, ending at the master battery, which sends the data for the whole bank to the inverter over its own cable. A single battery's screen shows its own figures — 105 Ah rated, 38 Ah left — while the master shows the whole system: 1,260 Ah rated, 496 Ah left, 39%. From the master's screen we can open any of the twelve batteries and see what is happening inside it.
Commissioning
With the breakers closed, the inverter found the system: batteries, the generator and the load, with no grid at all — the site is, in effect, in a forest. In the battery settings we set the lithium mode, which gives the same data exchange as the inverter maker's own batteries, a total capacity of 1,260 Ah, and a charge and discharge limit of 300 A. We deliberately stay below the inverter's 350 A, so it does not work at its limit all the time and lasts longer.
Then we enabled charging from the generator and closed the generator breaker. The charging power climbed on the inverter's screen, its fans started, and the master battery showed 200 A of charge for the whole bank — about 17 A on each battery — with every battery in charge mode and no errors.
How the system works
Gas from the underground tank runs a 30 kW generator in a separate building. The generator makes AC power, the inverter charges the batteries from it, and the batteries supply the production building. In practice the generator is a large charger for the battery bank: it runs to refill the bank, not to follow every change in the load.
What this means for a project in the UAE or the GCC
The same architecture works here with solar panels in place of — or next to — the generator: the inverter takes the panels' power during the day and the bank carries the evening and the night. The differences are the climate and the rules. Heat matters more than anything for battery life, so placement and ventilation come first, and grid connection rules depend on the emirate or country. See solar battery storage in the UAE & GCC for how we size and build such banks, or send us your brief.
Frequently asked questions
How much battery does a 20 kW UPS need?
It depends on how long the load must run on batteries. This system has 1,260 Ah at 51.2 V, about 64.5 kWh: at the 300 A limit the bank itself gives about 15 kW for roughly four hours before losses, the generator covers the rest of the 20 kW, and at a typical partial load the bank runs much longer.
Can LiFePO₄ batteries of your build work with a Deye inverter?
Yes. The BMS communicates with the inverter in its lithium mode, the same data exchange as the inverter maker's own batteries, so the inverter sees the real state of every battery.
Why connect twelve batteries in parallel instead of one large battery?
Parallel 48 V batteries share the current — about 17 A each at 200 A of system charge here — are easier to move and install, and one battery can be serviced without stopping the others.
Why limit the inverter to 300 A when it allows 350 A?
So the inverter does not work at its limit all the time. A margin below the maximum extends its life.
Can this system run on solar instead of a generator?
Yes. A hybrid inverter takes solar panels directly; the battery bank stores the daytime energy for the evening and night, and the generator becomes the backup.
Do you build systems like this in the UAE and the GCC?
Yes. We build and test batteries in Dubai and deliver across the UAE, Saudi Arabia, Qatar, Kuwait, Bahrain and Oman; tell us the load, the hours and the site.
Sources
- IEC 62619 — safety requirements for lithium cells and batteries in industrial and stationary applications
- UN Manual of Tests and Criteria, section 38.3 — transport tests for lithium cells and batteries